Chinese New Year (CNY) Risk Assessment & Supply Chain Mitigation Plan

I. Introduction of Chinese New Year (CNY)

 

As the Chinese New Year (CNY) holiday period is approaching, we would like to proactively highlight the potential impacts to manufacturing operations and the supply chain, as well as outline the actions we are taking to minimize disruption to our customers.

Chinese New Year is traditionally associated with temporary factory shutdowns, labor mobility, and logistics constraints across China. These factors may affect production schedules, material availability, and delivery lead times during a defined pre- and post-holiday window.

Through early planning, capacity prioritization, and close coordination with our supply chain partners, we aim to ensure continuity of supply for key products and customers. This document summarizes the potential risks, mitigation measures, and recommended actions required to achieve this objective.

 

Chinese New Year & Supply Chain

II. CNY Overview & Industry Impact Context

 

Chinese New Year is the most significant annual holiday in China, during which manufacturing activities typically slow down or stop entirely for a period of time. In addition to the official holiday, the impact usually extends several weeks before and after CNY due to:

  • Early employee departures and delayed post-holiday returns

  • Reduced factory operating capacity before shutdown

  • Ramp-up inefficiencies after production resumes

  • Logistics congestion caused by concentrated pre-holiday shipments

Historically, these conditions lead to longer lead times, reduced flexibility for changes, and higher pressure on logistics resources across most manufacturing sectors.

III. Potential Impacts to Customers Due to CNY

 

1. Manufacturing Impact

During the CNY period, customers may experience:

  • Reduced production capacity or temporary production suspension

  • Limited ability to accommodate urgent orders or last-minute changes

  • Delays in tooling modifications, sampling, or engineering validation

  • Longer response time for non-standard production requests

2. Supply Chain Impact

From a supply chain perspective, potential impacts include:

  • Extended lead times for raw materials and components

  • Temporary material shortages or allocation constraints

  • Higher minimum order quantities imposed by upstream suppliers

3. Logistics & Fulfillment Impact

Logistics-related risks may include:

  • Limited availability of export booking space prior to CNY

  • Increased congestion at ports and inland transportation hubs

  • Extended transit times and delayed customs clearance

  • Reduced shipment frequency during and immediately after the holiday

IV. Risk Level Assessment for Chinese New Year

 

Based on our preliminary assessment:

  • High-volume or customized products are more sensitive to CNY disruption

  • Products with complex supply chains or long material lead times carry higher risk

  • Orders confirmed late in the pre-CNY period face increased delivery uncertainty

Risk levels will be managed through prioritization and early execution, as described in the mitigation actions below.

V. CNY Mitigation Actions – Manufacturing

 

To minimize manufacturing disruption, we are implementing the following measures:

  • Pre-CNY Production Pull-In: Advancing production schedules for confirmed orders where feasible

  • Capacity Prioritization: Allocating available capacity to key SKUs and strategic customers

  • Process Readiness: Completing tooling, sampling, and engineering approvals before the holiday

  • Buffer Strategy: Building reasonable safety stock for selected products, subject to demand confirmation

  • Operational Alignment: Aligning shutdown and restart plans with factory partners in advance

VI. CNY Mitigation Actions – Supply Chain & Logistics

 

On the supply chain and logistics side, our actions include:

  • Material Pre-Booking: Securing raw materials and critical components ahead of CNY

  • Inventory Lock-In: Confirming material availability for priority orders

  • Logistics Planning: Reserving shipping capacity with forwarders where possible

  • Shipment Cutoff Management: Defining and communicating recommended shipment cutoff dates

  • Alternative Planning: Evaluating alternative routes or shipment modes when necessary

VII. Customer Coordination & Required Actions to Prepare CNY

 

To ensure smooth execution, we kindly request customer support in the following areas:

  • Confirm order quantities and forecasts as early as possible

  • Place orders before the recommended pre-CNY cutoff dates

  • Complete approvals (samples, specifications, artwork, documents) without delay

  • Identify priority SKUs or projects that require special attention

  • Maintain close communication during the pre- and post-CNY period

Early confirmation will significantly improve production planning accuracy and delivery reliability.

VIII. Key Dates & Timeline for Chinese New Year

 

  • Last recommended order placement: [To be confirmed]

  • Pre-CNY final production window: [To be confirmed]

  • Factory shutdown period: [To be confirmed]

  • Production restart window: [To be confirmed]

  • First post-CNY shipment estimate: [To be confirmed]

Specific dates may vary by product and factory and will be communicated separately where applicable.

IX. Conclusion & Commitment From GEMS-MFG

 

We remain fully committed to supporting our customers throughout the Chinese New Year period. While seasonal disruptions are unavoidable, early planning, transparent communication, and close collaboration allow us to significantly reduce their impact.

We appreciate our customers’ understanding and cooperation and look forward to working together to ensure a stable and reliable supply before, during, and after the CNY holiday.

Partner with a trusted manufacturing expert to accelerate your product development. GEMS-MFG is the comprehensive solution provider here for you. As a one-stop custom manufacturer, we provide a wide range of services, including rapid prototyping, mold making, injection molding, CNC machining, die casting, and more.

Whether your requirements involve intricate prototypes or precision parts, GEMS-MFG is committed to delivering an efficient and cost-effective solution tailored to your needs. Contact us today [INFO@GEMS-MFG] to explore our offerings and receive an instant quote. Your manufacturing goals are our priority.

 

Chinese New Year (CNY) Risk Assessment & Supply Chain Mitigation Plan

Why GEMS MFG?

Integrated Factory Resources

We are your one-stop manufacturing solution provider for customized products with the joint effort & support from our 120 partnership subcontractors mainly for the production of metals & plastics. We can expand much faster but the top management decide to keep GEMS a compact, dedicated and professional company, which allows our team to really focus and deliver on your projects without any excuse or compromise. We strive to be a long-term, reliable and trustworthy partner of our customers rather than just being a contractor, and look forward to growing the company with customers’ success.

Manufacturing Veteran Team

With the passing years, we are proud to build up a manufacturing veteran team with rich experience and full expertise to fulfill your specific demand. From mold making, injection molding, die casting, stamping and sheet metal, to 2nd processes like CNC machining, oil spraying, powder coating and chrome plating, and then assembling and packaging and related, we always have someone in house to be an expert to resolve the issues in different stages of product development. We also specialize in providing charger, cable and hub, plus other electronic accessories that support a complete set of product.

Strong Project Management

“Think global, execute local” is the principle of our work. Time, quality and cost are the three key elements to be considered throughout the product development from concept design to mass production. A detailed plan with weekly conference call update is a critical gateway to ensure these three key elements are successfully implemented, also assuring that all parties are on the same page. Communication is the Secret to Success . Everyone works independently to take care his own job, but together we are a team to get things done and are your daily eyes and ears onsite in China.

Flexible Operation & Customization

We offer a wide variety of products, such as mold, component and assembly product, and certain value-added services. For logo or branding product, we have in house resources to complete a color mix that can perfectly match a brand’s unique colors in fast and cost-effective way. Understood the client needs production parts but having a hard time to find a vendor since the order quantity is as low as 1000 or lower. GEMS is well set up for low volume injection molding or die casting projects. Surely our team is also capable of building SPI Class 101 mold that is designed & made for 1 million cycles or more of producing the same high quality parts consistently.